PlanningThursday, November 19

A proposed South Augusta data center goes to a Planning Commission hearing Monday

The Augusta Morning News teamFrom Thursday’s edition · 1 min read · 2 sources

ShareEmailFacebookX

If you've got thoughts on the proposed South Augusta data center, Monday's hearing is where to share them. Community members can voice their concerns before the makes its recommendation on 3G Investments LLC's rezoning and special exception requests.

  • When: 2 p.m. Mon., Nov. 23; reports differ on the venue
  • Asking: rezone about 383 acres, plus a special exception
  • Sites: 1538 and 1550 Four H Club Road; 3806 Mike Padgett Highway
  • Next: Planning Commission recommends; Augusta Commission decides

WRDW lists the Augusta Commission Chambers as the venue, while WJBF says the Augusta Municipal Building, so check before you go. Here's what's still open. Planning Director Lisa Cameron wrote that noise, water and electricity studies are required with a separate site development application, and didn't say whether the developer has submitted any. The Development of Regional Impact () form says an electricity study “has been requested from the energy supplier,” and it gives no water figure for filling the closed-loop cooling system.

The proposed campus would draw big power and carry a big price tag

600 megawatts
peak electrical load listed in the regional impact form
$3 billion
estimated worth at build-out, per the form
4.2 billion
kilowatt-hours a year at 80% of capacity, per a draft analysis

Source: WRDW

Neighbors have questions. The hearing was first set for Nov. 2 at 3 p.m., then postponed to Dec. 7 at the applicant's request, then moved to Nov. 23. Anthony Braddix, who lives about a mile from the site, questioned the changes and said planning meetings are “always during a time when people is at work.”

The data center ordinance passed twice before Monday's hearing

  1. Sept. 15Commissioners approve the data center ordinance on first reading, 6-5
  2. Sept. 28The developer files its applications
  3. Oct. 6Commissioners approve the ordinance on second reading, 6-5
  4. Nov. 2The hearing was first scheduled for 3 p.m.
  5. Nov. 23The Planning Commission will hear the requests at 2 p.m.

Sources: WRDW, WJBF

Sources: WRDW, WJBF

Read it in the full edition

All news news
  1. WJBF13 hours ago

    THE KULTURE | Quamid and LUV’s “He Is”, on WJBF

    This week’s throwback video is “He Is” by Quamid and LUV. You can watch the full video here: The Kulture streams now on Thursdays at 12:30 PM EST, 2:30 PM EST, 7:30 PM EST, and 11:30 PM EST on WJBF6+ available on Roku TV, Amazon Firestick, Apple TV, Samsung TV devices.

  2. WJBF18 hours ago

    Troopers urge safety for Thanksgiving travel, on WJBF

    NORTH AUGUSTA, Sc. (WJBF)- Thanksgiving is less than a week away and that means many families are beginning to head out of town. But before heading out travelers are being encouraged to plan ahead and to stay safe while driving on the roads. Whether it’s a short drive around the CSRA or long road trip,